Know a new house's wind features before you climb the ladder.
A builder's free link shows every feature as drawn and specified.
- Drawing set
- 19 sheets
- Code review
- 28 checks
- Materials order
- 145 lines
- G-001
- G-002
- C-101
- A-101
- A-201
- A-301
- A-302
- A-401
- A-501
- A-601
- A-602
- A-701
- S-001
- S-101
- S-201
- E-101
- E-201
- P-101
- M-101
Today, a wind mitigation form asks how a house was built, and you arrive after the building is done.
You look for the plan details the form asks for
in the owner's paperwork
You judge what the roof covering hides
the deck nailing and the straps
You piece together the four-point basics
from labels and receipts
With XYZ, every feature the form asks about is listed as the plans specify it, with the sheet it comes from and what to confirm as built.
You open the builder's link
no account needed
You check each feature on site
with the sheet it comes from
Three jobs change most for inspectors, and here is each one with XYZ.
01
The wind mitigation form
Today
Some items on the form take a phone call before you can mark them.
With XYZ
Roof covering, deck attachment, roof to wall connectors, roof shape, secondary water resistance and opening protection are listed as drawn and specified, each with its sheet.
Design criteria
15 values
- CodeFBC Residential, 8th Ed. (2023), ASCE 7-22
- Risk categoryII
- Ultimate wind speed Vult140 mph
- Allowable wind speed Vasd108 mph (FBC-R R301.2.1.3)
- Wind speed fromHillsborough County default, not confirmed for this lot
- ExposureB
- EnclosureEnclosed, GCpi +/-0.18
02
What you cannot see
Today
Whatever stays hidden behind the soffit, you mark from a look in the attic and what you know about how houses like it were built.
With XYZ
The connector schedule and the roof deck attachment as specified tell you what should be there, and each item says what to record as installed.
Quantities from the drawings
145 lines
- Ready-mix concrete, 3,000 psi61.5 cu yd
- CMU 8x8x16, standard2,135 units
- 2x4 SPF stud, 10'-0"257 studs
- Self-adhered underlayment (ASTMÂ D1970)23 rolls
- Window A: 6'-0" x 5'-2"3 ea
- 1/2 in drywall 4x10, walls182 sheets
- Vanity mirrors, frameless, 36 in high35 sq ft
145 lines across 15 trades, each measured from the drawings.
03
The four-point basics
Today
On a house that was just built, the four-point basics still have to be documented as if nobody knew them.
With XYZ
Each comes as the plans specify it: the roof covering, the service and panel, the supply piping and water heater, and the heat pumps.
Drawing set
19 sheets
Here is what the builder's link gives you, free, before you set foot on site.
- 01Every wind mitigation feature as drawn and specified, item by item
- 02The sheet or order line behind each feature, with what to verify on site
- 03The four-point basics as the plans specify them
What it costs
Free
- Inspector view of any shared projectFree
The builder shares the house once, and you can open it as often as the job needs.
Questions inspectors ask
How does it help on site?
It tells you ahead of time what the plans specify for each item, so your time on site goes to confirming what is there.
Which form does it follow?
Florida's uniform mitigation verification form, OIR-B1-1802, the one insurers there ask for. The same features matter on any wind mitigation inspection.
Where does each feature come from?
Each one names the sheet or the order line it comes from, such as the roof plan, the connector schedule or the window schedule, and says what to confirm as installed.
Open the sample house, and you will see what a builder's link gives you before an inspection.
Doing something else in real estate? See how XYZ helps the other roles